Debrecen Faces Potential Water Shortages in Summer 2027 Due to Rising Factory Demand

Debrecen, Hungary’s second-largest city, could face serious water supply difficulties as early as summer 2027 because of the growing demands of major industrial plants, according to documents obtained by local news outlet Debreciner.
The findings raise concerns that the city may struggle to provide enough water for both factories and residents during periods of peak consumption.
An investigation by Debreciner, based on documents released following a public information request, suggests that municipal and state-linked organisations have been aware of the potential problem since early 2026. The newspaper argues that residents were not informed of the findings, despite the implications for the city’s future water supply.
A study by Debrecen Infrastructure Development Ltd (DIF), a company owned by the local authority, found that five major industrial investments could require an additional 11,264 cubic metres of water per day during peak periods in 2027 compared with 2025. This includes the first phase of Chinese battery manufacturer CATL’s factory, but excludes its planned second phase.
The DIF’s calculations used a daily supply of approximately 12,000 cubic metres from the Keleti Main Canal, provided by the Tiszamenti Regional Waterworks (TRV) in 2025. The company also considered an increase in this supply to 22,000 cubic metres per day.
Even with that additional capacity, the calculations showed a shortfall of 1,264 cubic metres per day during peak periods in 2027, based on the industrial developments already included in the assessment. The figure does not account for the planned second phase of CATL or any growth in residential water consumption.
The DIF warned that summer demand could be difficult or impossible to meet with the available resources. Its managing director, Ferenc Kun, wrote that Debrecen had already faced a precarious situation during heatwaves in 2025, before the major new factories were operating. The city’s reservoirs had to be filled to capacity in advance and were almost completely emptied by the end of the hottest periods.
Kun described this as a risky and unsustainable arrangement during prolonged heatwaves, when the city consumed more water than the system could replenish.
The documents also reveal the scale of the planned expansion. The Debrecen CATL plant reportedly requested cooling water of 4,450 cubic metres per day for its first phase, while the second phase is expected to require 5,406 cubic metres daily. The latter figure is higher despite the second phase still being in preparation.
The DIF concluded that supplying the expansion would require further increases in water deliveries from the TRV. However, the national water utility had already told the National Investment Agency (HIPA) in March that increasing capacity beyond 22,000 cubic metres per day would not currently be feasible. Even after additional infrastructure investment, the maximum achievable supply was estimated at 30,000 cubic metres daily.
That would provide an extra 8,000 cubic metres compared with the current capacity, only moderately more than the combined additional requirement of 6,670 cubic metres for CATL’s second phase and the shortfall identified in the DIF study.
Debreciner also highlighted that the assessment did not include rising household demand, even as new residential areas are being developed to accommodate the growing workforce. Climate change and increasingly severe summer heat could further increase domestic consumption.
The newspaper reported that the South Korean EcoPro plant may also require an additional 3,000 cubic metres of treated wastewater daily from 2028. Meanwhile, water extraction from the Keleti Main Canal was restricted during the summer of 2026 because of low water levels in the Tisza.
The findings do not establish that household taps will run dry in 2027. They do, however, point to a potentially serious mismatch between available supplies and projected demand. Debreciner has also questioned how much Debrecen’s mayor, László Papp, knew about the assessments. The mayor previously said he had learned of the relevant correspondence only through the newspaper’s reporting.
This message was taken from this source and rewritten by artificial intelligence.
This news story was taken from dailynewshungary.com and rewritten by artificial intelligence as part of a project of the ACM Cyprus New Technologies Development Unit.